East Borderland Community Housing Inc. Rotating Header Image

Project Updates

Project Status:

  • Staff confirmations on project selection and moving forward.
  • Approval of Project Development Funds ($60,000)
  • Approval to proceed with working drawings.
  • Approval to proceed with geothermal study and civil engineering .
  • Awaiting formal loan approval from Manitoba Housing and Minister of Housing.
  • Awaiting final legal arrangement on land .
  • Construction started October 2011.

Project Schedule:

  • Tendering late summer 2011
  • Start construction October 2011
  • Projected occupancy Fall 2012